Construction of the Hesseling Residence

2679 Lunde Lane, Mt Horeb, WI

 

Excavation Phase

10/14/06 - 1/13/07

Driveway construction, dig and pouring of the foundation/basement, well, septic, geo-thermal install.

Roughing Phase

1/12/07 - 3/23/07

Building the exposure walls, laying the steel and decks, framing the rest of the walls and laying the trusses.

Mechanicals Phase

3/26/07 - 5/30/07

Roofing, HVAC, Geo-Thermal Loop Field, Septic Install, Well & Water System, etc.. 

Finish/Trim Phase

5/29/07 - ????

Insulation, Drywall, Interior Doors, Hardware, Trim, Flooring, Cabinets, Fixtures, etc..

Landscaping/Cleanup